Current Worksites
House #86 Schedule
Leslie Shephard-Long Family
3758 Walter Ave.
Bloomington, IN 47403
Below is a list of our upcoming worksite dates. Please check this page regularly as its content changes frequently.
| Date | Tasks | Volunteers Needed |
Sign Up |
| 9/13/2008 | Frame-Up Walls / Porch | 11 | OVER |
| 9/20/2008 | Trusses/Roof Decking | 15 | OVER |
| 9/27/2008 | Roof Shingles / Windows / Ext.
Doors *Start Sub-Contracting Rough-In |
15 | OVER |
| 10/04/2008 | Siding / Soffets / Insulation | 9 | OVER |
| 10/11/2008 | Siding / Drywall | 9 | OVER |
| 10/18/2008 | Siding / Drywall / Side Porch *Start Drywall Finishers |
9 | FULL |
| 10/25/2008 | Interior Painting / Install Luan *Start Finish Electric / HVAC / Install Vinyl Flooring |
5 |
Sign up! (afternoon only) |
| 11/01/2008 | Interior Doors / Cabinets / Pre-Paint Trim | 5 | Check back for sign up |
| 11/08/2008 | Interior Trim
Installation / Caulk Trim *Start Finish Plumbing |
4 | Check back for sign up |
| 11/15/2008 | Interior Trim
Installation / Caulk Trim / Touch Up Paint *Install Carpet |
4 | Check back for sign up |
| 11/22/2008 | Touch-Up Paint / Punch List | 4 | Check back for sign up |
| 12/06/2008 | Landscape / Clean Interior & Exterior of House | 9 | Check back for sign up |
DEDICATION: December 13, 2008