Summary of R&R 2012-2013

Subtotal by
Categories IUB IUPUI IUE IUK IUN IUSB IUSE Category
Bldg Envelope/Interiors 5,316,600.00 2,665,439.00 - - 60,000.00 100,000.00 20,000.00 8,162,039.00
Code 5,535,000.00 172,662.00 - - 42,760.00 300,000.00 210,000.00 6,260,422.00
Electrical/ Distribution 3,548,000.00 1,150,000.00 - 97,500.00 150,000.00 - 370,000.00 5,315,500.00
Elevator 1,353,000.00 200,000.00 - - - 200,000.00 - 1,753,000.00
Emergencies 1,509,000.00 402,375.05 - - - - 100,000.00 2,011,375.05
Mechanical 1,810,000.00 3,284,523.95 300,000.00 129,500.00 247,240.00 100,000.00 - 5,871,263.95
Roof 5,739,000.00 525,000.00 - - - - - 6,264,000.00
Site 3,563,300.00 - - 73,000.00 - - - 3,636,300.00
Steam/Chilled Distribution 200,000.00 - - - - - - 200,000.00
Water/Sewer 226,100.00 200,000.00 - - - - - 426,100.00
                 
Grand Total 28,800,000.00 8,600,000.00 300,000.00 300,000.00 500,000.00 700,000.00 700,000.00 39,900,000.00